Hi, when on CM25 i enter in a planned order already dispatched and change qty or dates the order automatically gets dispatched from that line, is there a way to avoid this, so that i can modify qty and don't have to reallocate then the order on a line?

Accepted Solutions (0)

Answers (2)

Answers (2)

rupesh_brahmankar
Active Contributor

Hello,

As I know this is as per standard SAP system design, when you change the dispatch planned order, which calculate new order finish date and deallocate the order and you need to dispatch order/operations afterwards.

Best Regards,

R.Brahmankar

Caetano
Product and Topic Expert
Product and Topic Expert
0 Likes

Hello

Whenever there is a change in the order quantity or dates, it needs to be rescheduled, so that new dates can be calculated, therefore, it is deallocated.

Regards,
Caetano

AdalbertoNeris
Explorer
0 Likes
Is there a way to mantain the schedule in that order? I change the date, and maintain in CM25?