on 2011 Aug 26 7:31 AM
Good day!
How do we automatically get a "Deactivation on" date in an Asset under Construction after a full settlement of an order (KO88)?
Transaction ABAVN doesn't work here.
Regards,
Marianne.
Dear Marianne,
This how the deactivation in settlement process goes -
Once the asset under construction has been completely settled (there are no more values in any depreciation areas), the system automatically deactivates the asset under construction. You can switch off this automatic deactivation using an indicator in the definition of transaction types 340/345.
Request you to please check your settings in AO76 for T.Type 340 & 345. In details check whether the Deactivate fixed asset checkbox is Ticked for both T.Types. Here the system recognizes to deactivate the AuC asset after FULL settlement.
I hope this helps you to solve your issue. If you have any doubts feel free to share - you are welcome.
Regards,
Pankaj A Bhalerao.
Have a nice weekend !
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
AUC is a type of a project as soon as you settle the AUC to main asset system automatically deactivate the AUC asset.Which mean you have already settle the AUC so no more entry required.
If you want to have more posting in AUC then you have to create the New AUC or try to reverse the Settlement document.
Regards,
Shayam
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
106 | |
8 | |
6 | |
6 | |
6 | |
5 | |
5 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.