Hello Experts,

On 31.03.2018, we have problem with the date in the document flow view. The documents which were created on 31.03.2018 had all displayed as 01.04.2018, however when I check the document header or view for the tables, the date were correct (31.03.2018).

My observation is due to previous logon time is 03 hrs. ahead of system time, date is changed.

Has anyone encountered it before?

Please help, from where system pick-up previous logon time.

Thanks in advance.

Regards,

Rajesh

View Entire Topic
JL23
Active Contributor

Can it be that those documents are from a company which is located in a different time zone than your SAP Server?

Have a look into OSS note 99579 - Document Flow dates not matching to document dates