Hi Experts,

In a performance based single cycle plan with call horizon as 100 % . The call is falling due in say next 15 days. IP30H is executed for next 20 days period. So the actual call object generated. But there was additional measurement document posted resulting in the call due today. But the background job of IP30H is not changing the planned dates after the call object is generated.

But manually IP10 scheduling with new start is able to generate call object for today. but as a planner , how can a planner how will he be able to pick these plans to do it manually. Is there a way to automate this IP10 new start in background job.

Regards,

Karthi

Accepted Solutions (0)

Answers (1)

Answers (1)

MTerence
Active Contributor
0 Kudos

Hi Karthik,

There is no option in standard to re-schedule a plan.

For one of my client, we have developed a program to do Re-Start using a date when the next order to be created.

Did you try giving the IP30H days more than 15 days.. say 30 days.

Regards