CTM Parameter ExtendForwardBinaryMode

yavuz_durgut
Advisor
Advisor
0 Kudos
249

Hello, we are having small receipts from CTM to supply a large demand in forward planning. How can we stop this behaviour? Is it something to do with ExtendForwardBinaryMode parameter? How is this parameter used? Any information is welcome.

Yavuz

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

As I am unable to see that note I assumed your question was how to use parameter? and your question gave that meaning.

What about capacity of production resource?

You are getting supply shortage due to capacity constraint

or any other reason?

You try it with additional sort sequence CTM qty by descending order-it prioritizes from larger demand qty to lesser one

Best Regards

vara

Former Member
0 Kudos

I don't know whether my reply has given you any clue.

Any way you are trying to see the result in sim version try it and you might have analysed the simulation of demand prioritization right.

Best Regards

Vara

yavuz_durgut
Advisor
Advisor
0 Kudos

Hello, thank you very much for the note 619050. I can use it in future implementations. BUt for current case I am dealing with small quantities of receipt, and parameter ExtendForwardBinaryMode.

yavuz_durgut
Advisor
Advisor
0 Kudos

Oh, one more addition, I know how to use parameters.

Former Member
0 Kudos

When I search for that note 680011 it is displaying that number could not be found.

Any way try to look at Note 619050, if that is the way explained to use parameter - you can go to contol menu on top of CTM profile and in drop down menu you select planning parameters - enter paraname and values as given in the note press back arrow and save the profile.

Best Regards

Vara

yavuz_durgut
Advisor
Advisor
0 Kudos

Sorry, the note is for checking yet. Not released.

Number 680011

Version 8 from 09.08.2006

Status For Checking

Set on 09.08.2006

Former Member
0 Kudos

Yavuz

Can you tell me

1. APO version

2. Demand prioritization sequence in CTM profile or Sort profile

3.Other parameters you have used in CTM profile

and one more thing some parameters are obsolete in SCM 4.0

see OSS 709569

Regards

Vara

yavuz_durgut
Advisor
Advisor
0 Kudos

Please Take a look at the Note 680011.

That note includes info on this parameter. The note is amended after my customer message. But I am not use how to use the parameter.

Our release is SCM 4.1 (CTM r4.2)

Forward Planning active. Sort profile is MBDAT.

Best Regards

Yavuz Durgut