Hello all,
I want to create PO from PR with NL001(Non-stock material) and SM0001 (Service product).
In "Process Purchase Requisitions (V2) ", I can create a PO if I select only non-stock material or only a service product. However, when I select both types of items together, the system does not allow me to proceed.
However, I can create PO from PR successfully using the "Create Purchase Order - Advanced" app.
Has anyone encountered a similar issue? Any insights or solutions would be greatly appreciated. Thank you!
Request clarification before answering.
Hi @kaya-ya
The issue occurs because the source of supply is missing in the purchase requisition. In the app "Process Purchase Requisitions (V2)", after assigning the source of supply to the purchase requisition, you will be able to create a purchase order.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 37 | |
| 23 | |
| 18 | |
| 6 | |
| 3 | |
| 3 | |
| 2 | |
| 2 | |
| 2 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.