While creating Customer Project via app 'Plan Customer Project' i am getting a standard waning message 'We recommend a maximum duration of three years'. I would like to know:
1. If this is just warning and i could carry on with Project duration more than 3 years?
2. Or not select project duration more than 3 years? and why so? what all other functionalities will be impacted in S4 HANA Professional Service Public cloud?
Regards
Request clarification before answering.
Hi @nilkpmg ,
the message that shows up is a warning message you can skip and use all professional service functionalities also for projects with a duration longer than three years. If the project is running this long it can be set up in this way, however, a lot of projects have a shorter duration.
Best regards,
David
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
119 | |
8 | |
7 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.