on 2012 Mar 19 4:26 AM
Dear Friends,
Before i go and tell you the issue, i want to explain you what i have done.
My Client requirement is to configure a Costing variant which only shows / estimates the cost of Materials. It should not take the Routing and OH Costs.
I have created a Costing Variant ZMAT, which i have selected the options below.
1. Costing type - 01 Standard cost estimate - (Standard price and Legal valuation)
2. Valuation variant
Material Valuation - Planned Price 1
Activity type / Processes - Blank - As i do not need any Activity cost included.
Sub-contracting - Net Quotation price and Net purchase order price
Ext. Processing - Price from operation and Net Quotation price
Overhead - Cost sheet blank
Now the issue is,
This costing variant ZMAT is only working for Raw materials. When i tried running it for FG / SFG, It is showing the below error in initial screen itself in CK11N
Object was not costed
Message no. CK060
Diagnosis
The system could not find any entries that are relevant to costing.
System Response
The system did not cost the object.
Kindly suggest where i am going wrong
Thanks,
Narasimhulu
Hi,
Please do below settings T.code: OKKN in this miscellaneous tab
If in register 'Misc.' there is set '0 Messages online' please change this into 1 or 2 'Log and save messages, mail active/inactive'. After changing this, the costing doesn´t terminate and you get a log. In this log you will find the messages, which are responsible for CK060. If you eliminate the causes of the responsible messages, message CK060 should no longer be issued.
Best Regards,
Ram
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Guys, good evening.
I just need your thoughts on configuring the Costing variant for only Material costs.
Excluding Activity costs, Overhead costs and Sub-contracting costs from Cost estimate.
I have achieved in excluding the Activity and OH Costs, but when i am excluding the Sub-contracting settings from Costing variant, while running costing for FG, SFG which is part of FG is taking the Standard price from material master instead of BOM.
Any thoughts.
Thanks
Hi Narasimhulu,
I assume system is looking for either BOM or Routing - check the Qty structure control in costing variant
GAN
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
BOM is available for the FG / SFG which i am running.
One more thing is, we have another costing variant which we use regularly for our costing and when i run with that costing variant, system is running costing and showing results.
Some where the Costing variant is not synchronizing correctly.
Please advise
Thanks
Hi Narashimhulu,
I know this issue was dicussed many times on the forums. Please the below thread
http://scn.sap.com/thread/2035572
Let us know if it still does not solve your issue
Hi Dear,
Please check the setting of the both costing variants try to reconcile both. I know you don't want to calculate Labor cost and Overhead. See are there any other differences apart from these two.If possible could you please attach the screen shot of quantity structure tab of the CK11N transaction
Actually, i have configured a Costing variant a year back and we are using that successfully.
New requirement is that we need to create a Costing variant which will only shows us the Material cost.
I have created a new Costing variant, but it is not executing. For the same FG/SFG, system is executing and showing the Standard cost.
OKTZ is fine, i made it as +++
Thanks
Hi,
I believve you are getting the error as the settings for the costing variant is incompelte (as you have not maintained the valuation variant for activity prices intentionally. As you have valid BOM and Routing I do not think the sytem will ignore or not consider the actiivty cost just because the valuation variant is not maintained for the same.
For a solution you may have to look at workarounds as I understand for your normal costing you want to include activity cost for this specific costing variant you do not want to include the activity cost.
One workaround which strikes me is that you create a separe CO Version for this and maintian a nominal price say 0.001 per 10000 units as the price and have the valuation variant point to this and look for the lattest available price.
Hope this helps you.
Varadharaajan
User | Count |
---|---|
107 | |
9 | |
8 | |
6 | |
5 | |
5 | |
4 | |
4 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.