Costing sheet not calculating the Overhead amount when the Standard Cost is created CK11N

CapriconRevanth
Discoverer
0 Kudos
352

Costing sheets attached to the costing variant through valuation variant working well in EPT system.

We created the same costing sheets in DEV system and transported them to TST system, we compared each entry of costing sheet between TST and EPT and were looking perfectly correct.

But when we created the cost estimate for the same material and plant both in TST and EPT, TST failed and EPT was successful, as it was calculating the Overheads through costing sheet.

We are not sure if this was due to Transport and we could not see any issues, unless there is a bug in the system while being transported

View Entire Topic
mdtariqul_alam
Participant
0 Kudos

Hi,

Check the routing where you have mentioned the cost center and kindly also check that you have maintain Per hour activity cost for this cost center through t.code KP26. 

BR.

Tariq Russel. 

 

CapriconRevanth
Discoverer
0 Kudos
Hi all, thanks for your support responding back to my query. In the costing sheet BASE where the cost centers and Activity Type combinations were maintained. But the PRODH instead of PRDOH was assigned, so this caused the issue in TST system because KP26 in TST was with PRDOH, the AT was rectified and issue got it fixed.