on 2018 Apr 18 12:41 PM
Hi,
I have a case where cost estimate was allowed to be saved even if the BOM was not maintained. As routing was maintained system updated the price accordingly. On further analysis, I understood that message CK 424 "No BOM found" is an information message. I tried to change the message class as well as message type to E via OBMSG & OBA5 but that didnt work out.
Any thoughts on how can I restrict the cost estimate for materials where no BOM is maintained?
Help others by sharing your knowledge.
AnswerRequest clarification before answering.
Hi, Thanks for the inputs. It worked. But still when I run CK40N even if the message is an Error, the cost estimate is saved with Routing costs. Any idea?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 29 | |
| 14 | |
| 14 | |
| 6 | |
| 5 | |
| 4 | |
| 4 | |
| 3 | |
| 3 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.