on 09-17-2007 10:46 AM
Res all,
how to define cost center for work center ?
and how to define activity types for SETUP , MACHINE , LABOUR etc activity?
plz send details with TCODES
regards
Hi
The flow is like this:
1 Create activity type:
2 Assign the activty type to the cost center and plan the activite here.
3 U can do a cost center plan for this activity and calculate the plan activity price
4 Create a work center
5 assign the cost center to the work center. U cannot assign more than once cost center to each work center.
6 Once u assign the cost center- in the cost center tab of work center u will be in a position to assign the activity type defined in the first stpe against SETUP, LABOR & MACHINE.
Hope this help you.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ajay
For defining Activity types T code KL01
Then you have to plan the activity by using T code KP26
Here you assign the activity type to particular cost center
To define cost center T code KS01
Then in CR01 (work center) u will assign the cost center and activity type
to that cost center
Thanks
Ansuman