Res all,

how to define cost center for work center ?

and how to define activity types for SETUP , MACHINE , LABOUR etc activity?

plz send details with TCODES

regards

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi

The flow is like this:

1 Create activity type:

2 Assign the activty type to the cost center and plan the activite here.

3 U can do a cost center plan for this activity and calculate the plan activity price

4 Create a work center

5 assign the cost center to the work center. U cannot assign more than once cost center to each work center.

6 Once u assign the cost center- in the cost center tab of work center u will be in a position to assign the activity type defined in the first stpe against SETUP, LABOR & MACHINE.

Hope this help you.

Former Member
0 Kudos

Hi Ajay

For defining Activity types T code KL01

Then you have to plan the activity by using T code KP26

Here you assign the activity type to particular cost center

To define cost center T code KS01

Then in CR01 (work center) u will assign the cost center and activity type

to that cost center

Thanks

Ansuman

Former Member
0 Kudos

what abt cost center?

regards

Former Member
0 Kudos

HI

T code for defining cost center KS01

Thanks

Ansuman