Hi everybody,

I am facing a problem in creation of Routings.

The problem is that we have a way too much information in Routing master data. and when the end users try to create a routing from scratch it takes too much time for them to do it. in this case we offered them to use copy from option for the routing creation and it works very well. however when we use copy from option it copies routing description (group counter description) of referred routing and that data is unchangeable.

My question - is there any way of changing that routing description data or copping that routing without routing description.

I am leaving some pics to illustrate the issue.

Thanks indeed.