Hello,

I am trying to copy actual COPA line items to a plan version. When i run KE1A system sums the line items according to copa objects and lost referance (billing) document number. I need the document number for reporting purposes.

How can i keep the field rbeln while actual --> plan copy ?

Thank you

adam.

Accepted Solutions (0)

Answers (1)

Answers (1)

waman_shirwaicar
Active Contributor

Hi,

During copy the data in COPA is not read from line items but from segment level or corresponding summarization level if exists. Hence your requirement does not seem feasible.

Maybe you could export your actual data to excel and then try to upload this excel in planning. Try with a small example and see if this works.