Hi There
i Have Non Configurable semi Finish Material with Strategy Group ( 20 : Make-to-order production ) in mrp3 view . material have BOM , Routing , Prod Ver
this material have sales order and , When I want to convert sales order to production order whit CO08 , After Select production Version, system gives the following error message :
==========================================
Message no. CO684
The component cannot be allocated to an individual stock because make-to-order production and engineer-to-order production cannot be executed with this order.
A possible cause is that you are trying to create an order with reference to a sales-order/project, where an account assignment to a sales order/project is not allowed in the settlement profile that is assigned to the chosen order type. This is inconsistant.
The following responses are possible:
Order processing is cancelled.
The system resets the special stock indicator back to the original value.
===========================================
Does anyone have a solution?
Request clarification before answering.
User | Count |
---|---|
101 | |
16 | |
6 | |
5 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.