on 2021 Jun 01 12:31 AM
hi,
i hope you can help me, i have one issue, and it’s about a production order un second or third level.
the main kmat have a class that have one characteristic with 2 values, this value i need that will be used for select one of the 2 raw materials that it’s used for all one project.
so, the structure is.
-main kmat (level 1)
-kmat in the second level, (level 2)
-phantom E50 ( level 3)
-material E ( prefab part that it’s made by sheet metal) ( level 4)
-phantom E-50 (configurable material)(level 5)
-raw material 1
-raw material 2
the issue it’s that i can’t read the characteristic from the main kmat for select the raw material needed.
any idea? i my experience, it’s posible read the characteristics just in level 2 and 3, but before 3 i don’t have any idea how to do it.
Request clarification before answering.
Hi mafh,
There two SAP notes that are kind of vintage, but I would still suggest you review both and validate if the 'fix' would apply in your scenario.
456510 - Material variant in multi-level configuration
513288 - Material variant as a component in multi-level configuration
Cheers,
Luis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
mafh,
There are two possibilities only.
1) if you have non configurable assembly in between , create variants
2) change the non configurable assembly to configurable assembly.
Thanks
RD
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Since, we are creating the production order for the E part , we cannot select the raw material based on the characteristics in kmat above the E part.
You may have to create two Variants of E containing the two raw materials and then select E based on the characteristics of root KMAT (1st level)
Thanks,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi dominic, thank you for your answer.
any suggestion? the issue it’s that we have in our actual structure hundred of e parts, and we are out of time for create all the e variant parts, and we want to find an easy way for fix this issue.
i was thinking that perhaps i can’t inherit the characteristic to the e parts, and add the the special class that define the raw material to all the e parts.