on 2024 Nov 21 7:46 PM
Hi Experts,
User created a PROCESS ORDER in S4, changed the process order qty in COR2 and saw that the components quantity also changed proportionately based on BOM.
But another Order for same FG Material, User changed the process order qty in PPDS Planning board /SAPAPO/CDPS0 Txn with option "Adjust Proportionately", but the Qty (UoM - PC) is not proportionate for the RM component. There is +/- 1 or 2 units difference for the RM. In this case expected value is 8. There is no Component scrap % as well.
Why is it behaving so? Maybe since PPDS process the info from Live cache?
Looking for your inputs pls.
Regards,
Jeffrey
Request clarification before answering.