Can anybody explain <b>complete cycle for MTO (SG 20) in terms of Tcodes</b> from <b>sales order creation to settlement of production</b>
Thank you
Hi,
Assume FERT below ROH
<b>FERT:</b>
sales order creation VA01
Check the order in MD04
Run mrp MD02
Stock list MD04
Double click pl order.Convert planned order into production order through MD04
ROH:
Double click purchase req.Convert purchase req into pur order through MD04
Goods receipt MIGO 101 mvt against pur order
Check the stock in MD04
Goods issue against prod order MB1A 261 mvt
Confirm the opn CO11N(operation wise) or CO15(order)
Goods receipt MB31 101 mvt
Check FERT stock in MD04
SALES:
Delivery VL01N
Billing VF01
Hope it will help.
Regards,
Dharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
109 | |
8 | |
8 | |
6 | |
5 | |
5 | |
5 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.