on 2024 Sep 05 7:58 PM
Hello Expert
After PO create this amount not show in Report .
Request clarification before answering.
From ME23n on the PO created, what do you see when you navigate through Options: Environment, AC commitment documents?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Patil,
You need to make sure that commitment management is activated in controlling area first in OKKP. if it is activated check that commitment and prediction ledger is activated for commitments in the following path: Controlling-> Cost Center Accounting-> Budget Availability Control for Cost Centers-> Check Prediction Ledger
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.