CM50 and CM01 capacity planning data not matching

harshv12
Participant
0 Likes
302

Hello All

when i am executing CM01 and CM50 for the same work center i can see difference in required capacity. 

Eg. In planned order in detail scheduling tab there are 2 operation for that work center. One operation 0010 is have 0 capacity and other 0170 is have 5 hr capacity requirement.

In CM01 it shows capacity requirement as 5 hr just for 0170 operation while in CM50 it shows 10 hr (5 for 0010 and 5 for 0170).

 Any idea how this can be fixed.