Hello,

I have a requirement to show both process order and maintenance order requirements for a work center in CM01.

Normally, CM50 indicates the locking/ system non availability of a production work center, because of maintenance requirements.

But I would like to use same work center for both process order and maintenance activities and understand the capacities from both areas in CM01. How to achieve this functionality? please suggest

Thanks,

Accepted Solutions (0)

Answers (3)

Answers (3)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Blocked capacity or maintenance order capacity will not appear in CM01, as per standard SAP design. Transaction like CM21 or CM50 here you can check the dates which mentioned in the PM order as basic start and finish dates will be appeared as blocked.

For more details please refer SAP Consulting note 385059 - Capacity requirements for PM order header not visible in CM01

And old discussion on same topic,

Work center Capacities not reduced in CM01 but PM Order is displayed

Best Regards,

R.Brahmankar

0 Kudos

Hi Kumar Semmalai,

Thank you for the response. Yes this is the integration we perform normally and where in different work centers are used for the scenario. But I would like to see both PM and PP requirements in CM01 for a single work center, meaning I want to use same work center for both PM and PP activities.

Normally the formulas for PP work center and PM work center are not the same.

So how to achieve this functionality.

Thank you,

S S

kumar_semmalai
Active Contributor
0 Kudos

Hello S S,

you will get the answers for your requirement by searching the SCN forum.

Here is the one :

https://answers.sap.com/questions/10984181/pm---pp-integration.html

Best regards,