Closing Project

Former Member
0 Kudos
855

Hi,

I am trying to close the project via CJ20N, I moved the cost from AUC TO FIX Asset.however  i am greeted with following error,

1.Error when processing asset under construction (AuC) for WBS element
IAL-600063-01 .Message no. CJ824

2.It is not possible to deactivate in fiscal year 2012.Message no. AY135

Can anyone  please advise .

  Thanks

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos
Former Member
0 Kudos

Hi pillai

Thanks for ur replay.i cant able to open both links.our network admin kept some authorization for openings some links.

can u send me screen short pls.

Former Member
0 Kudos

Hi pillai,

ya saw those note i think its not relevant.the detail error msg is given below.Pls Can u advise.

Error 1.

Error when processing asset under construction (AuC) for WBS element
IAL-600063-01

Message no. CJ824

Diagnosis

While editing an asset in construction for the WBS element, an error
occured.

System Response

Processing stopped.

Procedure

Go to the asset in construction for the WBS element and correct the error
that appears there.

2.Error

It is not possible to deactivate in fiscal year 2012

Message no. AY135

Diagnosis

The fiscal year change has not yet taken place for the new fiscal year
2012.

System Response

The system cannot carry out the deactivation on the date that was
entered.

Procedure

Carry out a fiscal year change for the new fiscal year 2012, or deactivate
the asset in fiscal year 2011.

Former Member
0 Kudos

Hi

I solved by doing 2012 financial year period opening.