on 12-07-2010 1:05 PM
Hi Friends,
We are planning to close all existing scheduling lines & we'll create new schedule lines for the same POs. so please guide how to close all schedules at a time & how to upload new schedule lines.please guide with T codes.
Regards,
Hari Krishna B
Hi,
Make delivery schedule to zero, Goto ME32L and change validity date of agrrement and go to header- details, select appropriate date and fix , now the schedulling agreement will be automatically gets closed.
Hope this may help you............
For uploading the SA in MASS use t-code----
MEMASSSA
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Guru,
We have created the schedules using ME38 for particular SA. Currently, we are doing one by one scheduling agreement and closing the pending schedule lines. We are having approximately 400 scheduling agreements. Closing pending schedule line are taking longer duration.
We want to close all schedules which are not delivered / short receipt from the suppliers for a given plant. This is exercise needs to be done on daily basis.
Subsequently, day schedule to be uploaded in schedule lines.
MEMASSSA is not giving desired results.
Regards
Hari
| User | Count |
|---|---|
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.