on ‎2021 Apr 23 1:08 AM
Hi guys
I have created new plant and activated material ledger
When shall I run the CKMSTART Production run of material ledger
Before the extension of material to new plant or after the extension of material to new plant
Already material Ledger is activated in system because it is S4 Hana system
Request clarification before answering.
Hi aamna
The ML should be active, before the material master can be created in a plant, so you need to set ML active first using CKMSTART.
Thanks & regards
Sanil Bhandari
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi aamna
I do not remember having locked all materials before CKMSTART. The below blog explains the steps for Material ledger start up
https://blogs.sap.com/2018/02/01/material-ledger-and-actual-costing/
Thanks & Regards
Sanil Bhandari
Sir,
All previous material ledger periods need to be closed in production before going live(What do we mean by closing previous period of material ledger before going live). {In number of cases chances are that material ledger gets productive in one month (say 04,2012) and then business tries to execute closing after the completion of the next month ( say 05, 2012)[Please even explain this point in detail] .}
Hi aamna
I have not understood your new question. If there is a new plant, you will make it productive in a particular month. Once the transactions are booked in a period, you would perform month end close in ML. I have not quite understood your question on ML close for other plants, which are already productive and the closing of period for the new plant, which would become productive. It would help if you specify your query in a bit more simple terms so that I can help you.
Thanks & Regards
Sanil Bhandari
| User | Count |
|---|---|
| 28 | |
| 27 | |
| 18 | |
| 4 | |
| 3 | |
| 3 | |
| 3 | |
| 3 | |
| 3 | |
| 3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.