on 2011 Aug 02 3:07 AM
Dear All,
We are doing ck40n and try to release the cost estimate. But error CK711 Future standard cost estimate is locked for this company code B.
We have another company code A already completed cost estimate. But we found some materials cannot be release and Future Cost in Materail master. Also said no authorization on company C, and D which is totally not related.
Can anyone give me some hints ?
Thanks a lot
Request clarification before answering.
Hi
Go to CK24 and check if marking allowance is issued for the required company codes
In Ck40N, i hope you have specified Plant in Selection parameters.. Else, it would not give error for any unrelated comp code
br Ajay M
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check two things.
1>There is no authorization issue while releasing.
2>Secondly for those materials for which future costs exists delete the same through CKR1.
Regards,
Divraj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
86 | |
11 | |
9 | |
8 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.