cancel
Showing results for 
Search instead for 
Did you mean: 

CK11N price and CO03 Cost Trend - Raw Material

former_member291
Participant
0 Kudos
712

Hello CO Experts,

This is regarding with 'Planned Price 1' cost in Costing 2 tab.

When I run the CK11N the material price for RM is fetching as per my valuation variant for 'Planned Price 1' for Rs.100 but when PP team create the Planned order to Production order the value of RM in cost trend is Rs.500 which is picking from the RM MAP price. also at the time of Goods Issue time 500 of cost is consuming.

Why the system is picking the MAP price of Rs.500 for RM in the production order? as when I have a Priliminary cost estimate of RM Rs.100?

We also having PS module to control the cost. this is impacting Rs.400 at the time of project.

In this case, there is no point to have a planned price 1 cost in Costing 2 tab, correct?

Regards

Saravanan

Accepted Solutions (0)

Answers (2)

Answers (2)

aulia_rasyidi1
Explorer
0 Kudos

Hi Saravanan,

1. Find in your planned/production order what planned costing variant is used.

2. then check valuation strategy for planned costing variant in OPL1, what price is used for valuation of material.

Regards,

Aulia

former_member291
Participant
0 Kudos

Hi Aulia,

Thank you for your response.

I checked in OPL1 and I see the strategy maintain for 'Valuation price according to price control in Materal Master', in my case do I need to change it to 'Planned price 1' for both Costing Variant PLAN and Costing Variant ACTUALS? pls assist.

Regards

Saravanan

indrajit_das
Explorer
0 Kudos

1. Check your valuation variant assigned to your costing variant: the material valuation strategy must have planned price 1 as a strategy that CK11N is picking up.

2. Goods movements are always valuated at the material standard or MAP price depending on the price control of the material

3. As for other costs like activities, you can have them as part of your routing and have them calculated in CK11N as activity prices

former_member291
Participant
0 Kudos

Hi indrajit_das

Thank you for your responses.

I agree with your point no 1 and 3.

Regarding point no 2,

If system picks the MAP/Std price then this is leading to Price difference issue at the time of Variance & settlement.

Reason:

My CK11N price of RM is Rs.100 strategy 1 from 'Planned Price 1', so through out the project completion this is my planned price, and system also should validate the plan and actual cost based on the planned price 1 in Co03 cost trend correct? but my case system is validating the MAP value in Co03. note: We have also implemented Project system module, hence all stock movements will be happening thru the Special Stock 'Q' only but not thru the Normal stock.

so in my case planned price 1 senario will not effectively working since integrating with PS module ?

Regards

Saravanan