cancel
Showing results for 
Search instead for 
Did you mean: 

CJCO do not calculate Actual amount

0 Kudos
147

Dear all

During CJCO run the program didn't take into account 2014 actuals. On specific WBS element we have some Assigned amound in 2014 (in CJ31), but in CJCO we have 0 in Actual column. As result, whole budget was carried forward to 2015 which is incorrect.

I've tried to reconstruct project info and availability control (CJBW, CJEN, CJBN), but it doesn't helped.

I've tried BPCARRYF report for analysis, but it returns error AP147.

Please advice what else can be checked?

Accepted Solutions (1)

Accepted Solutions (1)

0 Kudos

This was error in program. SAP issued correction 2124310.

Assigned points to myself ))

Answers (1)

Answers (1)

MarinkoTolic
Advisor
Advisor
0 Kudos

Hi Philipp,

Maybe note SAP 1048588 will help in your case. In the note text you can find the explanation of what is beeing considered as actual cost in the perspective of the budget carryforward. Maybe this differs from what you consider as actual cost. CJCO can be executed several times. So if too much budget has been carried forward, the budget can be pulled back.

Best regards

Marinko