CJ40 Detailed Planning options not active

Former Member
0 Kudos
734

Hi Experts

I wish to do Detailed Cost Planning for my WBS elements, but when I go to transaction CJ40 >> Extras >> Detailed Planning, the options are grayed out (inactive). So I am not able to do detailed Planning through CJ40.

Can sombody have an idea how it can be rectified.

Thanks

JOHRI

Accepted Solutions (1)

Accepted Solutions (1)

Former Member

I think you are trying to access detailed planning from CJ40 in overall value screen. Detailed planning is available for fiscal year wise. Change the period from overall to any current or any fiscal year and now check again, detailed planning will be active now

Former Member
0 Kudos

Thanks a lot.

It has solved the problem

emmayoung
Participant
0 Kudos
thanks a lot, it hans solved my problem

Answers (1)

Answers (1)

nitin_patoliya
Active Contributor
0 Kudos

Check your planning profile - OPSB have you maintained relevant CE group /Costing Variant etc ?