on 2010 May 24 8:28 AM
HI
Organizational assignments are not managed as time-dependent in the asset master record.
We want to change the assignment to a cost center, which is in another PC.
The system then automatically run ABUM with appropriate standard transaction type as a default for the posting transaction.
Which standard transaction type is appropriate to reflect change in balance sheet side in PCA ?
Request clarification before answering.
The best for this is to use the transaction ABUMN - Transfer within Company Code and not to make the change with AS02
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.