on 2024 Feb 09 8:28 AM
Hi, I would like to know if it is possible to change the storage location type (e.g. raw material, finished goods, semi-finished goods) after they have been confirmed in CBC under the org. structure activity? I don't seem to find a way to do this.
Request clarification before answering.
Yes, you cannot make any changes once you have confirmed and completed. However, it will not make any serious impact on the follow-on configurations or in the project.
Maybe, you can give a try through "Implementation activities" app directly in customizing tenant, but I'm not sure this will allow you to change.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please refer this blog from SAP, which explains your case
Deletion of Organizational entities in SAP S/4HANA Cloud, Public Edition
Thanks