cancel
Showing results for 
Search instead for 
Did you mean: 
Read only

Change the profit centre in the existing cost centre master

t123455
Explorer
0 Kudos
1,875

Hi all,

my client wants to change the pc field in the existing cost center. example-Profit center A is assigned to cost center 1.Now profit center B needs to be assigned to this cost center 1. my questions are-

1.What will be the implications if we made that change?

2. Do we need to change all the PC intergration point (Like material, sales order etc) with new pc?

3. Do we need to do the changes in all the affected area manually? or the system will automatically post into new pc?

Thanks in advance for your input.

Best,

Mira

View Entire Topic
Neeraj_Jain1
Active Contributor
0 Kudos

Hello t123455,

Please refer below SAP thread in which detailed process/implications have been mentioned.

https://answers.sap.com/questions/5978455/change-the-profit-centre-in-the-cost-centre-master.html

Confirm if it works for you.

Regards,

Neeraj Jain

t123455
Explorer
0 Kudos

Sir,

thanks for sharing.

i have gone through the blog. unfortunately does not answer to my questions above.

Neeraj_Jain1
Active Contributor
0 Kudos

I have shared a SAP thread not blog, please check.

t123455
Explorer
0 Kudos

Hi, i have seen that using KS02 we can reassign the pc in cc..however i am still looking for the answer if it will have na impact on other areas..like do we need to change material master, sales order etc also?

For me, one blog is opening not a SAP threat.

Thanks,