on 10-10-2011 7:45 AM
Dear,
We are changing the price control of FG from moving average to std. But when change price control, giving message "Only price control "V" is possible for split valuation".
Kindly suggest how to change the price control from "V" to "S".
Regards
Biswa
Hi,
Changing the price control from "V" to "S" is posible but cannot make change in the following two cases:
1. If the material master record is set up as a valuation header record for a material subject to split valuation.
2. If the standard price comes from costing and is not equal to the moving average price
More check the notes: 72147, 1118703 & 882259
Regards,
Biju K
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Price is coming from Costing. Plz tell is there any way to change the "Price Control"
Hi Ranjan,
1. Its not readily advisible to change the valuation control of the material since it will cause many inconsistencies in almost every dependent functions.
2. You cannot change the val ctrl if the material has Split Valuation and Split Valuation is possible only for MAP materials
3. If you still want to change the val ctrl from V to S, then you need to empty all the stocks and close the docs viz. PO Prd Order, PR Stock in Transit etc.
4. After zeroing you should de-activate split valuation for the material then try changing the val ctrl.
You need to take legitimate care as your costing related data will change a lot, you should consult your FICO person before doing so.
Regards
Shiva
Hi Ranjan,
In material master "V" indicates Moving Average price while "S" shows that Standard price.
you must involve finance and costing dept before this change.
When you change the Price control indicator in Material master,you must have to check weather for that finished product moving average price and standard price is same or not.
After changing the Price control from "V" to "S",If price is not correct in material master then you need to take a help from FICO person and maintain the correct price in system.
You can maintain the correct price from MR21 transaction code.
Thanks
Sam
Hi Ashish,
You are right but most of time both price are same for FG.If there is any price change is availblable at that time it will effect price change account
When price contrl indicator "V" is availabe at that time price is avalable in moving average price.We must have to maintain the standard price for that finished material through MR21.
If Material ledger is activated then it must be posible to change the price control indicator.
Thanks
Sam.
Hi,
This was helped me to change over 100 materials' prices easily.
Thank you so much.
Thanks,
Hasitha.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I think it will be better if you make a new material code and close all the transactions related to old material code. Changing price control from V to S as suggested by many can be complicated.
Regards
Sangeeta
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please stick to basics, for not changing the moving average prive to std for split valuated materials. (Valution category). where as for valution type you can use either V or S.
BR,
Krishna
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
For this use t.code oms2 in this select your materiel type FERT for this maintain price control as standard.
And for fert always in stranded price only.
Thanking you,
Edited by: A.Purihella on Oct 10, 2011 8:52 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.