on 2023 Jan 11 8:35 AM
Hi Experts,
Greetings !!
Our business is a Food processing industry. They have change over time which will be taken into account when they change Production from one product to other product.
Example:
Similar way they have a fixed Change over matrix.
Master Recipe setup:
We use PP-PI here. Each Product carries only one phase. Example: The Master recipe of Roasted Cashew Product will have only Roasting operation. 0010 operation & 0020 phase.
So considering the above, whether it is possible? If yes, how to meet this requirement? What setup needs to be done for it in Recipe and Resource?
Kindly advise experts as this is new for me.
Regards,
Jeffrey
Request clarification before answering.
Hello jeffrey.pepito
The standard way to implement that is the functionality of Setup Matrix. It is customized in Production -> Capacity Requirements Planning -> Master data -> Routing data -> Define setup matrix
However that functionality is apparently not supported in PP-PI:
Therefore, I think you are limited to a custom enhancement in the area of capacity planning:
Best regards
Dominik Tylczynski
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Dominik,
Greetings !!
Thank you for throwing some light on the Setup Matrix.
So now since it's not relevant for PP PI and also excluding custom enhancements, is there any other option/way or work around to achieve this requirement? Like using Recipe Offset functionalities, anything like that?
Regards,
Jeffrey
User | Count |
---|---|
93 | |
39 | |
7 | |
6 | |
3 | |
3 | |
3 | |
2 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.