on 02-15-2011 4:05 PM
Hi,
I need help! I have a maintenance plan with a counter. This plan has been started and scheduling has being occured. This moment, the count is damage and I need to change maintenance plan for another on. My question is it'is possible to do?
Thank you for your attention,
Best Regreats,
Sara Silva
Hi,
It's very much possible that you can replace a counter. Please go through the following link page 56.
[http://help.sap.com/printdocu/core/print46b/en/data/en/pdf/PMEQMEQ.pdf]
This is normal phenominan that this counters can go bad.
We can replace and change the present counter value and start counting. May be once you complete the settings on meas point, you may have to reschedule your maintenance plan again.
Regards,
NNR
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Sara
How did you solve this issue?
This link [http://help.sap.com/printdocu/core/print46b/en/data/en/pdf/PMEQMEQ.pdf] is broken.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Yolima,
I made a substitution in the own counter and not in the maintenance plan. In the next reading register (transaction: IK11, in the menu: Edit -> Replace Counter, there three options, choose the one that best fits) can you replace the counter. Basically the counter number keeps just readings are changed. Pay attention, because the first reading will not use.
I hope I have explained!
Best regards
Sara Silva
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.