on 2015 May 13 2:11 PM
Hi,
updating employees in CATS with WBS will produce actual cost in WBS, however the CATS with network and activity is not producing actual cost in activity rather it is only producing confirmation. Is there anyway I can use CATS to update actual cost to cost activity without having confirmation?
Thanks
Request clarification before answering.
Hi All,
Thanks for you supports. Finally an information from sap.help put light on this issue. what it says that if you change the confirmation parameter of activity control key to confirmation not possible, then running CAT7 will post cost to CO without having activity confirmed.
Thank you
John