Capacity planning with Alternate UOM

Expert
Active Contributor
0 Likes
466

Is it possible to have the capacity planning in alternate UOM ( like we had CM01 in OP System ) ?

Accepted Solutions (1)

Accepted Solutions (1)

Expert
Active Contributor
0 Likes

Capacity Unit of Measure will be considered from work center and it is Time - Hours/Minutes/seconds. and the work center capacities can only be managed with UoM - Time units. Hence as of today it is not possible the way we have in OP

Tamil
Discoverer
0 Likes
Hi,I do have same requirement to define capacity in alternate UOM. I do remember this was possible in SAP APO PPDS, any idea how to do this in s/4 HANA eppds?

Answers (0)