Hi Experts,
I am currently setting up capacity planning at our customer.
They have production orders with multiple operations. When scheduling the order (in the screenshot you see the operatios for one order), I see that these operations are starting before the previous operation is finished?
Any idea why this is happening?
Thanks!
Request clarification before answering.
Hello,
Please check if there is overlapping setting is activated between the operations in the operation details. If yes, you can choose 'No overlapping' setting and schedule the order and save. Please ensure that, you have operation dates for all the operations in the sequence in the order after scheduling.
Thank you.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
92 | |
11 | |
9 | |
9 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.