I have following issue in CM01 transaction:

When I see laod for the work center for a production order in hours , say 100 hours. But when I assign operation split for that operation (say 4 splits) it shows process duration as 25 hours (in production order routing), but when I see the same order in CM01 then capacity requirements as 25 hours in place of 100 hours. How can I solve this issue.

Thanks in advance,

PPQM USER

Accepted Solutions (0)

Answers (1)

Answers (1)

madlercm
Active Contributor
0 Kudos

I think that in CM01 you see each split separately. Look for the other splits, they may be there on other dates.