What are the Prerequisites for capacity scheduling table ?
Request clarification before answering.
Note that the app considers only bottleneck operations of an order that are identified (based on the production line) in the production version.
Maintain the right production line otherwise you will not be able to schedule orders for the production version.
Make sure that the correct number of individual capacities are maintained for process industry orders if you have phases running in parallel. Otherwise, the phases are scheduled sequentially (even in parallel phases).
Additional Information : https://help.sap.com/docs/SAP_S4HANA_CLOUD/2bba750d1e124e1ea2a039bb1cd9b6c5/8d2e44f0c279408ba2790e9a.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
87 | |
13 | |
10 | |
5 | |
4 | |
4 | |
3 | |
2 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.