on 2025 Feb 06 2:43 PM
We have two alternate BOMs and Production Versions for a semi--finished material. When we select the first production version, it uses the second Production Version/BOM. When we select the second production version it also uses the second Production Version/BOM.
Other odd things, the second BOM does not allow for entry of the Valid From date. When we add a component, it automatically fills in the current date and does not allow it to be changed.
Things I have checked:
System: Public Cloud
Any ideas what I am doing wrong?
Request clarification before answering.
Hi @VickiG1
It could due to the Bom Usage involved . There is standard delivered customizing in
Define Order of Priority for BOM Usages but maybe for the production version involved a usage is selected that doesnt have an entry in Define Order of Priority for BOM Usages
Unfortunately its not mention what usage you are using but its the only thing i can think of
Best Regards
Enda
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
10 | |
10 | |
9 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.