Once the PO has been released, it should not allow us to cancel release, already used the indicator as 1 i,e can not be changed but also i am able to cancel the release in ECC. Please suggest on this
Request clarification before answering.
Hi,
I would suggest a work around - configure output message (NACE) and trigger the output automatically (MN04 - set date and time as 4 - send automatically upon saving) after PO release. If the PO is outputted, system will not allow to cancel the release from ME29N. You may test the same.