Can we define validation rule for production date should not be more than 31 days from posting date?

jithendrashiva
Participant
0 Kudos
237

Hi Experts

can we define a validation rule where production date should not be more than 31 days from the day of posting date.

EX: if posting date is 01/12/2023 the production date should be within 12/31/2023 for document type KC.

Thanks & Regards

Jithendra Shivashankar

Accepted Solutions (0)

Answers (1)

Answers (1)

GavinMonteiro3
Participant
0 Kudos

Hi Jithendra,


I am assuming you want to place a validation on accounting documents.

Please refer below blogs to understand how such validations can be placed.

Create Finance Validation Rule using GGB0 for FB60 Transaction | SAP Blogs

Adding Validation to F-43 | SAP Blogs

In your case, you can keep the prerequisite as
Company code = '1001' AND Document Type = 'KC'.

Regards,

Gavin.