Can anyone explain how to maintain flexible replenishment lead time in S4HANA aATP with BPS?

papa261190
Explorer
0 Kudos
115

Dear Gurus,

Recently SAP has included the functionality to use API for Scheduling Consumers in order to retrieve flexible replenishment lead times using a Scheduling Schema for aATP.

I have read the documentation provided by SAP but honestly I feel a bit lost since it seems too technical. I thought it would be similar to the approach followed to Scheduling in BPS by maintaining durations and calendars in Fiori. However, it seems a bit more complex and I would like to know if someone can easily explain what and how it works.

Thanks a lot!!

View Entire Topic
michael_thinschmidt
Product and Topic Expert
Product and Topic Expert

Hi papa261190,

With the upcoming OP2025 S/4 Hana release this feature becomes fully available. Please have a look at my KBA 3502154 How to maintain checking horizon via BPS - for detailed information.

Right now, it is not possible to setup the horizon in another way - than the old way via total replenishment lead time/planned delivery time and/or goods receipt processing time. Sorry, you have to wait for the next release (OP2025).

best regards,

Michael

papa261190
Explorer
0 Kudos
THanks a lot!!!!! Your KBA is completely what I needed and good to know that we still need to wait for the next release 😞