We need hourly requorements mapped into schedule lines, I know we can manally update time in schedule line, is there a possibility to incluce time from MRP run automatically instead of creating schedule line at day level.
MM (Materials Management) MAN Material Requirements Planning SAP S/4HANA Cloud Public Edition Sourcing and Procurement
Request clarification before answering.
Hello @RanjithKumarM
I don't think so. MRP runs on daily basis, it plans in daily buckets.
Best regards
Dominik Tylczynski