on 2021 Oct 05 7:43 PM
Hi all,
I'm using BAPI BAPI_OUTB_DELIVERY_SPLIT_DEC to split outbound delivery and it's working fine.
the problem is that the commit is implicitely done inside the BAPI so no need to do it explicitely after the call.
My purpose is to execute the BAPI without commit and be able to write the commit explicitely after the call to write the changes to the DB.
Is there any way to achieve this ?
Or should I use another BAPI ?
Request clarification before answering.
Hi Occoro,
Please check the importing parameter TECHNCONTROL-UPD_IND, this might help you to execute the BAPI in simulation mode.