Dear All,
While making MIGO, I am getting error tht "Missing connection of material in plant to the material ledger
Msg: C+470
Can anybody please tell me where to do this configuration of material with ML
Request clarification before answering.
hi!
In my case, the valuation type view was missing: I created the view and it worked.
Regards.-
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check accounting 1 view of the material master. If Price Determination is blank that is your issue. You created the material prior to activating the material ledger. If the material ledger is not yet activated, you should be able to change the Price determination to 2 or 3, depending on your material. However, the ML Act. check box on the Acct. 1 view will not be checked for the material, you have to go to OMX1 to view if the ML is active. If the Price determination is 3 and needs to be 2, then use t-code CKMM to change it.
I have not found a solution to change a blank PD to 2 if the ML is active. I recreated the material with a new number.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 32 | |
| 17 | |
| 16 | |
| 6 | |
| 5 | |
| 5 | |
| 4 | |
| 3 | |
| 3 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.