on 2024 Jul 22 6:28 AM
Dear SAP,
When I create the pick task in ByD system, I found the field “End Date” is read only,
This field will impact our interface between ByD and WMS system.
Could we modify this field manually?
Best regards
Request clarification before answering.
Dear customer,
The planned end date in warehouse task comes from the requested delivery date in customer demand.
Therefore, this value cannot be changed neither from UI end nor from API side since it is calculated while checking ATP.
But you can choose change Planned Start Date & Actual Execution On instead while confirming warehouse task.
Best regards,
Gavan
SAP Technical Support, Public Cloud ERP