hi Community can someone help me to know the steps to bdugeting wbs in s4hana cloud
Request clarification before answering.
Hi,
after creating the Enterprise Project and it's WBS structure, you can plan the project budget using the "Import Financial Plan Data" app. Here, you can download the sample Excel template, fill out the necessary planning data (see example below) and upload this into the app.
Best regards
Varun