on 2014 Nov 17 11:57 AM
Hi All,
I have an Issue Availability Control on Budget of WBS element.
I have WBS element with Budget 100000 GBP and till now we have spended 79,273 and the Remaining
Budget is 20,727 GBP and my tolerance limit is set as Error message when it is 100%
Now, i am trying to create the Maintenance Order with Stock Material which has a Price of 20,727 GBP
here the budget is reached to 100%, then System should give an error message as Budget is Exceeded, but is allowing to the Maintenance Order,
Could you please me to block the work order when budget is exceeded even for Stock Materials which creates reservation from Maintenance Order.
Thanks & Regards,
Rajesh
GBP and
Hi Rajesh,
I am assuming that you have already linked the PM order to WBS element.
Check the budget profile / tolerence limits assigned to WBS element. Is it in error mode for all transaction types? as listed below..
++ All activity groups
00 Purchase requisition
01 Purchase order
02 Orders for project
03 Goods issue
04 Financial accounting document
05 CO document
06 Budgeting
07 Funds reservation
08 Fixed prices in project
09 Payroll
2. Are you just creating reservations on PM order? As accounting documents are posted only when Reservations are issued (actual cost gets posted) you will get error at that point.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Goto CJ31 > Display original budget > Extras > Availability Control > Analysis > check the assigned values. System uses this value to for availability control
Try reconstruction of WBS using CJEN, CJBN in sequence.
Also a basic question. How did you link the PM order with WBS element. Are you using ADPMPS or directly entering WBS element in Additional Data tab using IW32.
Thanks
Saurabh
Hi Rajesh,
In SPRO - Project System - Cost - Budget - Define Tolerance limits
1. Controlling Area
2. Budget Profile
3. Target Group if you are using ++ All activity groups try to change and use for each activity like PR / PO / Orders for project etc.
4. Action - 3 (Error)
5. Usage - 100%
6. Abs Variance - If required
7. Currency.
Then test your system, whether you get the error message.
Regards
Terence
User | Count |
---|---|
98 | |
8 | |
6 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.