Hi

I have a question regarding browser-based PI Sheets.

I’ve searched, but can’t find a solution to my scenario, although I’m certain it should be possible.

We make use of a monthly process order that will require continuous updates of movements and confirmations, using PI Sheet.

The current setup allows for only one PI Sheet per process order.

Since process messages are only created after completion of PI Sheets, this step can only be done at month-end.

Although it is possible to continuously update the PI Sheet, stock updates will only reflect at month-end during completion of PI Sheet.

How can we make use of PI Sheet to allow for daily updates by utilizing a single monthly process order?