In S4HANA system,  in program - CS_BOM_PRODVER_MIGRATION02, BOM status not equal to 2  but still production version is created for the BOM with status 02 (inactive).

Material has two alternative BOM (1, 2), Alt BOM 1 has BOM status 2 and Alt BOM 2 has BOM Status 1, but valid date and Lot size are same .

When program is run, it has consider both BOM for prod version. Why program is doing that.